OF INTEREST: First Highly Exceptional Load sails to ITER

​On Friday 14 November, the first Highly Exceptional Load (HEL) destined to the ITER site was loaded onto the container ship CMA-Ivanhoe in the port of Busan, South Korea, to begin its five-week journey to France.

On board is the 87-ton main body of one high voltage substation transformer unit (part of the ITER steady state electrical network) as well as 39 wooden crates packed with the transformer’s auxiliary components. The equipment was procured by the US and manufactured by Hyundai Heavy Industry in Ulsan, South Korea. Three identical transformers will be shipped to ITER in the coming months.
 
Ivanhoe should reach the Mediterranean harbour of Fos-sur-Mer on 19 December. There, the transformer main body will be unloaded and staged until 9 January 2015, when it will be transferred to a trailer.
 
The trailer will be loaded onto a barge to cross the inland sea Étang-de-Berre before travelling 104 kilometres along the ITER Itinerary, for delivery to  the ITER site in the early hours of 14 January.