IMAGE: Eleven segments to a completed basemat

The Tokamak Complex basemat will be poured in fifteen segments. Pour days are scheduled this month and next to complete the Tritium Building basemat (at the far end of the Seismic Pit); rebar work in the centre should be finished in July.